Update on 91 Fwy Construction Near RCC - March 1, 2013

 

Caltrans issues regular updates regarding contraction on the 91 Fwy corridor through Riverside. For more information from the Department of Transportation, visit their website at http://www.91hovproject.com/ for the latest news affecting RCC students and visitors.

Beginning Monday, March 3 through Friday March 15, lanes will be reduced in both directions between 14th Street and Central Avenue. The work will be conducted Monday – Friday during nighttime hours. The roadway in this area may be reduced to one lane in each direction at times.

EB 91 between 14th Street and Central Avenue
Monday, March 3 to Friday, March 15
10 p.m. to 5 a.m.
the next morning
Lane reductions
WB 91 between 14th Street and Central Avenue
Monday, March 3 to Friday, March 15
9 p.m. to 4 a.m.
the next morning
Lane reductions